Faced with the challenging combination of boring through both hard pack clay and loose sand in one continuous shot JMF was able to successfully complete a 1500 LF bore just outside of Laurel, MD. The final package included 6 HDPE conduits ranging from 4 – 8″. JMF brought in a full time mud engineer to ensure the highest possible success level for this project. JMF was also responsible for fusing, stringing, and proofing the conduits which totaled over 9,000LF.